Timeline for custom swimming pool construction

Step 1: Consultation and Design (1-4 weeks)
    

            Meet with designer/architect to plan the project in compliance with all limitations concerning size and location of the pool.
            Master Plans are drawn.

 

Step 2: Contract and Pricing (2 weeks +/-)


            The job is priced and a contract is written.
            The contract and pricing are reviewed by the homeowner and a payment schedule is discussed.

 

Step 3: Apply for County Permits (4-8 weeks)

            Review by County (3 days - 9 monthes)


            Obtain any necessary drawings (ie. structural drawings, grading plans, working drawings) for County permits.

 

Step 4: Apply for City Permits (2-5 days)

 

Step 5: Site Inspection and Preparation (1-2 weeks)
    

            Construction begins after permits are obtained.

 

Step 6: Construction (1 month +)
             The construction time will vary greatly by the scope of the job.
            Cost of construction is roughly $100,000 per month.

 